Citywide Projects

UPDATE: 04/01/25- This project is still in the utility relocation phase. Utility providers will be on the right-of-way of both sides of Telephone Rd. moving their lines in preparation for the widening. There is no scheduled start time as it is dependent on the relocation efforts.

The project will consist of removal and replacement of sub-grade and base materials, as well as replacement of the existing driving surface with concrete between SW 19th Street and SW 34th Street.  Including necessary curb and guttering, storm drainage improvements, sidewalks, streetscape and utility line replacement.  Telephone Road will also be widened to from 4-lanes to 5-lanes. This is a $10.9 million project. 

SW 19th st to SW 34th St

Update: 4/18/2025 COMPLETED

Update 4/8/2025: Crews finished laying all the asphalt yesterday for the new parking lot.  Action Safety will be there Wednesday, April 9th, to stripe the new parking lot.

Update 3/24/2025: The leveling and dirt work is continuing.  Once completed, crews will lay the asphalt.  Painting parking spaces and final touches after that.  Everything should be completed by early April if there are no weather delays.

Effective Monday, March 3, the Brand Senior Center parking lot will be closed due to construction for approximately 30 days. Senior lunches will be served at Eastlake Church 700 SW 134th St, Oklahoma City, OK 73170. Transportation will still run. If you are coming to the Brand Senior Center for any activities, we ask that you park in the back of the center. 

UPDATE 3/27/2025: The road is now open but there is still some construction remaining in the area.

UPDATE 2/14/2025:  Due to the inclement weather, the opening of Bryant Ave will be pushed back to the end of March 2025.

UPDATE 1/17/2025: The draining work is complete. Beginning, January 20, 2025, weather permitting, Silverstar will begin demolition of Bryant Ave. for reconstruction of the street.  It is anticipated that the reconstruction of the street will be completed by the end of February.  Construction of the bicycle/pedestrian trail and cleanup of the project area should be completed by the middle of March.

UPDATE 12/30/2024: Silverstar Construction will be finishing up the drainage project side next week.  

UPDATE 10/24/2024: Beginning Monday, October 28, the jersey barriers will be removed on Bryant.  Channel work will begin on the west side of Bryant, therefore crews must again close Bryant while work is being completed.  Completion date is first quarter of 2025, weather permitting.

UPDATE 10/1/2024: Jersey barriers were setup to open southbound only traffic on Bryant. Crews will start on the east side of the creek mid-week and complete that side before moving to the west side. 

UPDATE 08/26/24: There is a delay in opening Bryant Ave to SE 4th St. The heavy rains received over the past 6 weeks have caused the bottom of the channel to become unstable due to the continued inflow of groundwater from the bottom and sides of the channel.  A stable bottom is necessary to support the structural improvements. The design engineer is working on a solution to address the groundwater inflow. Once the solution is finalized an update will be posted here.  Also, once we have a completion date, we will update it here.

Beginning Wednesday, May 22, 2024, Bryant Ave will be closed from Parkway Dr. to SE 4th St. This will be a construction of drainage improvements on the east side of Bryant Ave.  

04/09/25 UPDATE: Per the City of OKC, SW 149th Street from Hudson Avenue to Vicki Drive will temporarily close to traffic from Friday, April 11, to Saturday, April 12. Crews are working on a storm sewer drain as part of the street widening project.

08/19/2024 UPDATE: Beginning Wednesday, August 21, 2024 Westmore Dr will be closed until May 2025.  The project construction manager has recognized potential safety concerns and has advised the City of Moore to close the street.

07/23/2024  Beginning Tuesday evening after 8:00pm, the Contractor performing the construction for the Widening of 149th Street in OKC from Santa Fe to Western will be closing lanes at the intersection of SW 19th St. and Santa Fe Ave. in Moore.  For Westbound traffic at the intersection, the existing left turn lane will be closed.  The existing westbound thru lane will be used for thru traffic as well as the left turn lane for traffic turning south during construction.  For Eastbound traffic at the intersection, the existing left turn lane will be closed.  The existing outside eastbound lane will be used for thru traffic as well as the left turn lane for traffic turning north.  The existing inside eastbound lane will now become the westbound lane for thru traffic.  Double yellow striping will separate the eastbound and westbound traffic west of the intersection during construction.  It is anticipated that construction will take approximately 8 months to complete.  Any questions regarding the project should be addressed with the OKC Project Construction Manager at 405-297-1768 or [email protected]

Update: 4/17/2025 The Briarhill box has been poured and crews are now backfilling.  The next step will be street paving and cure time for the bridge.  The project should be completed in 2 weeks, weather permitting.

Update: 4/10/2025 Crews are pouring the bridge deck this morning.  The project should be completed 3 weeks from today, weather permitting.

Update: 3/31/2025 Progress is being made.  Crews will be pouring the walls tomorrow.  Approximate opening date will be 5 weeks, weather permitting.

Update: 3/13/2025 Briarhill remains closed.  The estimated time of reopen is end of April, weather permitting.

Briarhill is closed between NE 19th & NE 20th for an indefinite period of time due to bridge failure.
 

04/10/2025- Norman St, between Main St & SW 1st will be starting a reconstruction.  Completion date is 2 weeks, weather permitting.

Update 04/17/2025- Norman St has been delayed due to the high probablility of rain over the next week.  This project should start up mid-week next week.

04/07/2025- Post Oak Road, panel repair work, 2-3 weeks for completion. 

Update 04/17/2025- Post Oak Project has been completed on one side of the street.  The other half of the street should be torn out next Monday, April 21, 2025.  Completion date is 2 weeks, weather permitting.

03/24/2025- City crews will remove the speed humps on SE 5th, SE 6th, SE 7th St, Heather Wood Dr and Beechwood Way and pour concrete back in the strips and level them. 

Update 04/17/2025- Heatherwood project should be completed on 04/18/2025, with all construction cones being removed.

03/15/2025- Crews will be installing new water main lines on Sunrise Dr, NW 24th St, N Janeway Ave & Vermeer Dr. This project is expected to be complete by July 30, 2025, weather permitting.

The Station Pool:
04/17/2025- The City has contracted Handy Dandy Handyman Inc. to repaint the Station pool for the upcoming pool season.  Completion date is Friday, April 25th, weather permitting.

Little River North Park Entry: 

UPDATE: 04/18/2025 COMPLETED

04/04/2025- Crews will be relocating the Little River North Park Entry Sign.  This sign was taken down years ago because of the construction on 4th. Completion date is Friday, April 25th, weather permitting.

Buck Thomas Park North Parking Lot: 
UPDATE: 04/18/2025 COMPLETED

UPDATE: 04/10/2025- Crews are completing some finishing touches on paint and installing signs.  This project should be completed in 2 weeks, weather permitting.

03/24/2025- The final layer of asphalt should be placed this week.  When the asphalt is complete, painting parking spaces and finishing touches are all that remains.  This project should be completed by the end of the month, weather permitting.

Veterans Memorial Park Trail Enhancements:
UPDATE: 03/18/2025 This project is nearing completion and should be finalized by mid-April, 2025, weather permitting.

02/01/2025- Construction of concrete flatwork, site signage, and the purchase and installation of benches and tables. We will be adding a shelter, granite walks and edge restraints, trees, and landscape beds.  This will be funded by a grant the Oklahoma Recreational Trails Grant for 80% to 20% city match that the City received.  

Happy Tails Dog Park: 
UPDATE: 04/18/2025 COMPLETED

UPDATE: 04/10/2025- The West Side Large Dog Park is Open and the East Side Large Dog Park is closed.

03/17/2025- East Side Dog Park will be closed on Monday, March 31st.  
We will be moving over the amenities to the West Side Dog Park in preparation for its opening on Monday, April 7th.  
The East Side Dog Park will be reopened on Tuesday, April 1st.  
The West Side Dog Park will be reopened on Monday, April 7th. 
East Side Dog Park will be closed on Monday, April 7th.

Little River Park Trail Relocation & Repairs:  
02/03/2025- Crews are currently working on relocating the trail in the middle of the park on the furthest west side that runs closest to the creek.  It is being relocated because of the washing out of the creek and safety concerns of the proximity of the trail to the edge of the creek has continued to get closer over time.  Also, crews will be working on repairing other areas of the trail that have cracked over time.  Completion date is Friday, May 16th, weather permitting.

Greenbriar Park Pavilion Roof Repair: 
UPDATE: 04/18/2025 COMPLETED

01/27/2025- The City has had the roof contracted out to Handy Dandy Handyman Inc. to be repaired as it was outdated and needed repair.  Completion date Friday, April 11th, weather permitting.

Contact Us