Citywide Projects

UPDATE: 04/01/25- This project is still in the utility relocation phase. Utility providers will be on the right-of-way of both sides of Telephone Rd. moving their lines in preparation for the widening. There is no scheduled start time as it is dependent on the relocation efforts.

The project will consist of removal and replacement of sub-grade and base materials, as well as replacement of the existing driving surface with concrete between SW 19th Street and SW 34th Street.  Including necessary curb and guttering, storm drainage improvements, sidewalks, streetscape and utility line replacement.  Telephone Road will also be widened to from 4-lanes to 5-lanes. This is a $10.9 million project. 

SW 19th st to SW 34th St

S Janeway and SW 10th & SW 12th
1/8/2026- Crews will be out replacing concrete panels.  This project will be completed by the end of January, weather permitting.

Eastern Bore
11/4/2025- 12 inch water line being relocated @ NE 12th St & Railroad tracks.  The east bound outside lane may be closed intermittently throughout this project.  This project should be completed by December 10th, weather permitting.

NE 12th from Lost Creek Dr to Sunnylane Rd
10/20/2025- Crews will be starting a total reconstruction project to rebuild the roadway.  NE 12th St will remain open for local traffic only during construction.  Construction should last about 30 days, weather permitting.
10/30/2025- 11/04 and 11/05/2025, NE 12th St will be closed to thru traffic from N. Bryant to Sunnylane.  Residents west of Clear Creek Rd should use N. Bryant. Residents east of Clear Creek Rd should use Sunnylane.  Crews will be replacing a tin horn across the roadway.
1/8/2026- The roadway is completely opened.  Crews will be out laying sod and stripping the street.  This project should be completed Friday, January 16, weather permitting.

Excess dirt storage  
07/07/2025- The City of Moore owns the property at 800 SW 4th St. Crews are currently storing dirt at this site from the SE 4th Street underpass project. This material will be used for future city projects.

Sunnylane to Sooner Rd on Indian Hills Rd
11/4/2025- 12 inch water line being installed on Indian Hills Rd.  Indian Hills Rd will remain open during this process.  This project should be completed by January 30, 2026, weather permitting.

NW 24th, N. Janeway, Shields, and Vermeer 
03/15/2025-Crews will be installing new water main lines on NW 24th St, N. Janeway Ave & Vermeer Dr. This project is expected to be complete by the end of September 2025, weather permitting.
10/16/2025- Things are slow moving with this project.  
11/4/2025- Crews had to adjust the project a bit, which has caused some delays.  This project is scheduled to wrap up by the end of 2025.

Moore Community Center: 
12/5/2025- Contractors will be repainting the Gym Doors at the Moore Community Center.  Work is set to begin by Mid-January 2026, with a completion date set for the end of January 2026, weather permitting. 

Buck Thomas Park Football Fields:
07/24/2025- Crews will be working on drainage issues for the football fields at Buck Thomas Park.  Construction is set to begin by the beginning of Mid-January 2026 with the completion date set for the end of January 2026, weather permitting. 

Buck Thomas Park Football Fields: 
1/8/2025- Contractors will be straightening and fixing the fence along the perimeter of the Football Complex at Buck Thomas Park.  Work is set to begin by Mid-January 2026, with a completion date set for the end of January 2026, weather permitting. 

Buck Thomas Park Dog Park: 
1/8/2025- Crews will be working on making the sidewalk ADA Compliant entering the East Side Large Dog Park at Buck Thomas Park.  Work is set to begin by Mid-January 2026, with a completion date set for the end of January 2026, weather permitting. 

Central Park Maintenance Yard Expansion: 
1/8/2026- Contractors will be working on Expanding the Maintenance Yard at Central Park.  Construction is set to begin by the Week of January 12th 2026 with the completion date set for the end of February 2026, weather permitting. 

Moore Cemetery: 
1/8/2025- Contractors will be adding electricity and lights to the South Pavilion at the Moore Cemetery.  Work is set to begin the Week of January 12th 2026, with a completion date set for January 16th 2026 , weather permitting.